A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
Correct Answer – 20