| 1. |
X, Y and Z can do a piece of work in 30, 40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed? |
| A. | 660/47 |
| B. | 640/47 |
| C. | 680/47 |
| D. | 665/47 |
| Answer» B. 640/47 | |