| 1. |
X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done. |
| A. | 6 days |
| B. | 8.1 days |
| C. | 5.1 days |
| D. | 7 days |
| E. | None of these |
| Answer» D. 7 days | |