X can do a work in 40 days. He worked for 8 days and then Y finished it in 16 days. If they work together, how long does it take to finish the work?

A. 10 1/3 days
B. 18 1/3 days
C. 13 1/3 days
D. 15 1/3 days
Answer» D. 15 1/3 days