1.

X can do a piece of work in 20 days and Y can do the 1/7th of the same work in 5 days. In how many days together they can complete the 11/14th of the total work?

A. 140/11 days
B. 15 days
C. 20 days
D. 10 days
E. None of these
Answer» E. None of these