MCQOPTIONS
Saved Bookmarks
1. |
X can completed a job in 12 days. If X and Y work together, they can complete the job in 62/3 days, Y alone can complete the job in |
A. | 10 days |
B. | 12 days |
C. | 15 days |
D. | 18 days |
Answer» D. 18 days | |