X can complete a piece of work in 30 hrs and Y can do it in 24 hrs. In how many hours will it be completed if they work together? |
| A. | 13.33 hrs |
| B. | 14.33 hrs |
| C. | 15.33 hrs |
| D. | 16.33 hrs |
| Answer» B. 14.33 hrs | |