1.

Which of these is not one of the phenomenons likely to occur while the phase I application of SPC?

A. Process likely to be out of control
B. Process changing its state continuously between in-control and out-of-control
C. Experiencing assignable causes
D. Large shifts in the monitored parameters
Answer» C. Experiencing assignable causes