Which of the following statements regarding PERT is NOT true? |
| A. | Each activity of PERT network has three different time estimates |
| B. | Expected activity time is estimated based on -distribution |
| C. | PERT is a deterministic model |
| D. | PERT network may have more than one critical path |
| Answer» D. PERT network may have more than one critical path | |