Which of the following is true about product backlog?

A. It is created in Sprint Planning Meeting
B. It contains a list of all desired features and is owned by the product owner.
C. It is a subset of the product backlog owned by development team and commits to deliver it in a sprint.
D. All of the above
E.
Answer» C. It is a subset of the product backlog owned by development team and commits to deliver it in a sprint.