MCQOPTIONS
Saved Bookmarks
1. |
Which of the following is true about product backlog? |
A. | It is created in Sprint Planning Meeting |
B. | It contains a list of all desired features and is owned by the product owner. |
C. | It is a subset of the product backlog owned by development team and commits to deliver it in a sprint. |
D. | All of the above |
E. | |
Answer» C. It is a subset of the product backlog owned by development team and commits to deliver it in a sprint. | |