MCQOPTIONS
Saved Bookmarks
| 1. |
Which of the following is not a change management process ? |
| A. | Log the changes |
| B. | Estimate impact on effort and schedule |
| C. | Review impact with stakeholders |
| D. | None of the mentioned |
| Answer» E. | |