1.

Which of the following depicts the correct order of the stages involved in grid integration of wind energy?

A. System operations physical connection planning
B. Planning system operations physical connection
C. Planning physical connection system operations
D. Physical connection planning system operations
Answer» D. Physical connection planning system operations


Discussion

No Comment Found