1.

When the number of product units outside the LSL and the number of product units outside USL are same, the process is called?

A. Centered process with poor process capability
B. Centered process with great process capability
C. Poorly centered process with poor process capability
D. Poorly centered process with great process capability
Answer» B. Centered process with great process capability