| 1. |
When slack of an activity is positive |
| A. | it represents a situation where extra resources are available and the completion of project is not delayed |
| B. | it represents that a programme falls behind schedule and additional resources are required to complete the project in time |
| C. | the activity is critical and any delay in its performance will delay the completion of whole project |
| D. | any one of the above |
| Answer» B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time | |