When slack of an activity is positive |
A. | It represents a situation where extra resources are available and the completion of project is not delayed |
B. | It represents that a programme falls behind schedule and additional resources are required to complete the project in time |
C. | The activity is critical and any delay in its performance will delay the completion of whole project |
D. | Any one of the above |
Answer» B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time | |