When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed
B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. The activity is critical and any delay in its performance will delay the completion of whole project
D. All of the above
Answer» C. The activity is critical and any delay in its performance will delay the completion of whole project