                                    When slack of an activity is negative | 
                            
| A. | It represents a situation where extra resources are available and the completion of project is not delayed | 
| B. | It represents that a programme falls behind schedule and additional resources are required to complete the project in time | 
| C. | The activity is critical and any delay in its performance will delay the completion of whole project | 
| D. | All of the above | 
| Answer» C. The activity is critical and any delay in its performance will delay the completion of whole project | |