1.
What is the value of the target value for the number nonconforming chart?
A.
np
B.
2p
C.
3p
D.
2np
Answer» B. 2p
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
The control limits for the p-chart and the standardized p-chart are different.
The values of control limits for the standardized c-chart are different from the control limits of the standardized p-chart.
Which of these does not have the LCL and UCL at ∓3?
Which of these correctly shows the correct values for standardized u-chart in the order of CL, UCL and LCL?
The center line of the np-chart is at _______
The LCL of the standardized p-chart is ________
The upper limit of the standardized c-chart for short production runs is ________
What is the value of the statistic plotted on the standardized np-chart?
What is the standard deviation of the number of nonconformities per unit, when the standardized u-chart is used for monitoring the process?
The attribute ui when plotted on standardized control chart for short production runs, the statistic plotted on the chart has the value equal to __________
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply