1.

What is the expected solution for the case when the T.W.C is lying above the J.H.C curve at all discharges?

A. By providing a simple concrete apron of length 5(Y₁ – Y₂)
B. By providing a sloping apron above the river bed
C. By providing a sloping apron below the river bed
D. Provision of a ski-jump bucket
Answer» C. By providing a sloping apron below the river bed


Discussion