1.

Using oracle scheduler you have scheduled two jobs, JOB_A and JOB_B, to run at 9:00 p.m. every friday. You want both the jobs to use a single resource plan, weekend_plan. Which task must have already been performed to enable you to achieve this objective?

A. A window must have been created with the WEEKEND_PLAN resource plan
B. A program must have been created with the WEEKEND_PLAN resource plan
C. A job class must have been created with the WEEKEND_PLAN resource plan
D. A window group must have been created with the WEEKEND_PLAN resource plan
Answer» B. A program must have been created with the WEEKEND_PLAN resource plan