| 1. |
Type 1 workers can do three times the work of Type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 8 Type 2 workers to complete the same task? |
| A. | 16 |
| B. | 17 |
| C. | 20 |
| D. | 18 |
| Answer» E. | |