1. |
Two persons A and B can finish a piece of work in 60 days, while A, B, and C can finish the same work in 40 days. How many days will C alone take to finish the work ? |
A. | 90 days |
B. | 100 days |
C. | 110 days |
D. | 120 days |
Answer» E. | |