MCQOPTIONS
Saved Bookmarks
| 1. |
Two concrete mixers of capacity 200 liters each are used in a construction site to produce 20 cubic meter of concrete. Ingredient charging, mixing and discharge times are 3 minutes, 7 minutes and 1 minute respectively. Assuming a time loss of 5 minutes per hour of operation, the total time in hours for the mixers to produce the required amount of concrete will be ___________ |
| A. | 10 |
| B. | 15 |
| C. | 25 |
| D. | 47 |
| Answer» B. 15 | |