To complete an assignment in 4 days, we need either 12 men or 15 women. 6 men take the project but stop working after 2 days. How many women will be required to finish the remaining work in 3 days? |
A. | 15 |
B. | 18 |
C. | 22 |
D. | 27 |
Answer» B. 18 | |