| 1. |
_ To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :$? |
| A. | 7 Days |
| B. | 7.5 Days |
| C. | 8 Days |
| D. | 8.5 Days |
| Answer» D. 8.5 Days | |