| 1. |
Three workers Trump, Putin and Jinping are appointed to do a job. They together started the job but Jinping left after 3 days when 37% of the job was done. The remaining job was completed by Trump and Putin in 7 days. The ratio of efficiency of Trump and Putin is 4 : 5. Find the number of days required by the slowest worker to complete the entire job alone? |
| A. | 22 days |
| B. | 20 days |
| C. | 24 days |
| D. | 18 days |
| E. | 30 days |
| Answer» F. | |