Three workers Trump, Putin and Jinping are appointed to do a job. They together started the job but Jinping left after 3 days when 37% of the job was done. The remaining job was completed by Trump and Putin in 7 days. The ratio of efficiency of Trump and Putin is 4 : 5. Find the number of days required by the slowest worker to complete the entire job alone?

A. 22 days
B. 20 days
C. 24 days
D. 18 days
E. 30 days