There will be deemed approval of registration if no action is taken on application

A. Within a period of 3 working days from the date of submission of the application
B. Within a period of 7 working days from the date of submission of the application
C. Within a period of 10 working days from the date of submission of the application
D. Within a period of 14 working days from the date of submission of the application
Answer» B. Within a period of 7 working days from the date of submission of the application