1.

There are two processes P1 and P2, whose periods are 50 and 100 respectively. P1 is assigned higher priority than P2. The processing times are t1 = 20 for P1 and t2 = 35 for P2. Is it possible to schedule these tasks so that each meets its deadline using Rate monotonic scheduling ?

A. yes
B. no
C. maybe
D. none of the mentioned
Answer» B. no