The optimistic, most-likely and pessimistic time for developing a new product are 12 months, 15 months and 17 months, respectively. Calculate the expected time in months. |
| A. | 12.00 to 14.00 |
| B. | 14.00 to 15.00 |
| C. | 14.14 |
| D. | 15.64 |
| Answer» C. 14.14 | |