1.

The latest finish time for an activity:

A. Equals the min. of LFT − t for all immediate successors
B. Equals the max. of LFT − t for all immediate predecessors.
C. Equals the max. of EST + t for all immediate predecessors.
D. Equals the min. of EST + t for all immediate successors.
Answer» B. Equals the max. of LFT − t for all immediate predecessors.


Discussion

No Comment Found