The labour rate variance can be calculated by the following equation: |
A. | (Standard hours - actual hours) x actual wage rate |
B. | (Standard wage rate - actual wage rate) x standard hours worked |
C. | (Standard wage rate - actual wage rate) x actual hours worked |
D. | Budgeted labour costs - actual labour costs |
Answer» B. (Standard wage rate - actual wage rate) x standard hours worked | |