| 1. |
The installation time for a gas turbine power plant is ______________ |
| A. | Comparatively less than thermal power plant |
| B. | Comparatively more than thermal power plant |
| C. | Equal to thermal power plant |
| D. | Very much longer than thermal power plant |
| Answer» B. Comparatively more than thermal power plant | |