| 1. |
_ The important file in making a PERT is$? |
| A. | An event can't be accomplished until activities leading to it are completed |
| B. | No activity from any event can be started from preceding event till it is completed |
| C. | Length of arrow has nothing to do with time |
| D. | All of the above |
| Answer» E. | |