The expected out turn of cement concrete 1 : 2 : 4 per mason per day is ________ |
A. | 6.5 m<sup>3</sup> |
B. | 1.5 m<sup>3</sup> |
C. | 2.5 m<sup>3</sup> |
D. | 5.0 m<sup>3</sup> |
Answer» E. | |