1.

The annual requirement of rivets at a ship manufacturing company is 2000 unit. The rivets are supplied in units of 1 kg costing Rs. 25 each. The costs Rs. 100 to place an order and the annual cost of carrying one unit is 9% of its purchase cost, the cycle length of the order (in days) will be ______.

A. 76.9457 days
B. 75.9457 days
C. 73.9457 days
D. 74.9457 days
Answer» B. 75.9457 days