The annual requirement of rivets at a ship manufacturing company is 2000 unit. The rivets are supplied in units of 1 kg costing Rs. 25 each. The costs Rs. 100 to place an order and the annual cost of carrying one unit is 9% of its purchase cost, the cycle length of the order (in days) will be ______. |
| A. | 76.9457 days |
| B. | 75.9457 days |
| C. | 73.9457 days |
| D. | 74.9457 days |
| Answer» B. 75.9457 days | |