The actual variable quantity is 50,the actual and budgeted overhead cost of allocation is $7550 and $4500 respectively then the variable overhead spending variance is |
A. | $182,500 |
B. | $152,500 |
C. | $162,500 |
D. | $172,500 |
Answer» C. $162,500 | |