State if the followings are true or false. For scheduling a project, it is necessary to: 1) Break down the project tasks into smaller, manageable form. 2) Find out various tasks and correlate them. 3) Estimate time frame required for each task. 4) Divide time into work-units.

A. True
B. False
Answer» B. False