Slack represents the difference between the |
A. | earliest completion time and latest allowable time |
B. | latest allowable time and earliest completion time |
C. | earliest completion time and normal expected time |
D. | latest allowable time and normal allowable time |
Answer» B. latest allowable time and earliest completion time | |