Slack represents the difference between the |
| A. | earliest completion time and latest allowable time |
| B. | latest allowable time and earliest completion time |
| C. | earliest completion time and normal expected time |
| D. | latest allowable time and normal allowable time |
| Answer» B. latest allowable time and earliest completion time | |