Seventy-five men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men should be employed to complete the work in the desired time ? |
A. | 300 |
B. | 325 |
C. | 350 |
D. | 375 |
Answer» B. 325 | |