1.

Server utilization (and, in this case, the mean number of tasks per server) is simply:

A. Server utilization = Arrival rate - Timeserver
B. Server utilization = Arrival rate + Timeserver
C. Server utilization = Arrival rate
D. Server utilization = Arrival rate / Timeserver
Answer» D. Server utilization = Arrival rate / Timeserver