| 1. |
Rohan wants to build a tank in 20 days for which he hires 60 workers. After 10 days, he sees that only 30% work has been done. To speed up the process and get the tank built in stipulated time, how many workers should work on the tank? |
| A. | 80 |
| B. | 120 |
| C. | 200 |
| D. | 140 |