Ramesh can complete a work in 12 days, working 7 hours a day. Suresh can complete the same work in 8 days, working 9 hours a day. If Ramesh and Suresh work together working 7 hours a day, in how many days can they complete the work? |
| A. | 7 * 3 / 23 |
| B. | 5 * 7 / 13 |
| C. | 6 * 5 / 13 |
| D. | 6 * 6 / 11 |
| E. | None of these |
| Answer» C. 6 * 5 / 13 | |