1.

Raman can do a work in 5 days, Jatin can do the same work in 7 days and Sachin can do the same work in 9 days. If they do the same work together and they are paid Rs. 2860, then what is the share of Raman?

A. 1260
B. 700
C. 900
D. 870
Answer» B. 700