Ram can do a piece of work in 5 days, and Sham can do the same in 10 days. With the help of Karan, they finished the work in 2 days. How many days would it take Karan to do the work ?

A. 5 days
B. 10 days
C. 15 days
D. 20 days
Answer» B. 10 days