1.

Ram alone can do 1/4th of the work in 2 days. Shyam alone can do 2/3th of the work in 4 days. So what part of the work must be done by Anil in 2 days, for them to complete the work together in 3 days?

A. 1/8
B. 1/20
C. 1/16
D. 1/12
Answer» E.