Radhe does 70% of some work in 15 days. Later, with Shyam’s help, she completes the remaining work in 4 days. In how many days can Shyam alone complete the entire work?

A. 35 days
B. 35.2 days
C. 35.3 days
D. 38.4 days
E. None of the above
Answer» D. 38.4 days