| 1. |
Q: Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ? |
| A. | 3 days |
| B. | 2 days |
| C. | 6 days |
| D. | 12 days |
| Answer» D. 12 days | |