1. |
Q: To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in: |
A. | 14 days |
B. | 12 days |
C. | 10 days |
D. | 15 days |
Answer» B. 12 days | |