Q: The ratio of efficiency of Arun is to Chitra is 5:3. The ratio of number of days taken by Bala is to Chitra is 2:3. Arun takes 6 days less than Chitra, when Arun and Chitra complete the work individually. Bala and Chitra started the work and left after 2 days. The number of days taken by Arun to finish the remaining work is? |
A. | 4 days |
B. | 5 days |
C. | 6 days |
D. | 9 days |
E. | None of these |
Answer» D. 9 days | |