1. |
Q: Ram can complete ¼ th part of work in 8 days and Shyam can complete 2/4 th of the work in 6 days and Naresh can complete ¾th the work in 12 days. In how many days can they together complete it? |
A. | \(6 {11 \over 17 }\) |
B. | \(5 {11 \over 17 }\) |
C. | \(8 {11 \over 17 }\) |
D. | \(7 {11 \over 17 }\) |
Answer» C. \(8 {11 \over 17 }\) | |