1.

Q: Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?

A. 8 days
B. 12 days
C. 14 days
D. 10 days
Answer» E.


Discussion

No Comment Found